Microsoft Project 2010, Managing Projects
- Exam Number/Code : 70-178
- Exam Name : Microsoft Project 2010, Managing Projects
- Questions and Answers : 63 Q&As
- Update Time: 2013-08-16
-
Price:
$ 119.00$ 79.00 -
70-178 Hard Copy (PDF)
-
70-178 Test Engine
Free 70-178 Demo Download
Test4pass offers free demo for Microsoft Business Solutions 70-178 exam (Microsoft Project 2010, Managing Projects). You can check out the interface, question quality and usability of our practice exams before you decide to buy it. We are the only one site can offer demo for almost all products.
Exam Description
It is well known that 70-178 exam test is the hot exam of Microsoft certification. Test4pass offer you all the Q&A of the 70-178 real test . It is the examination of the perfect combination and it will help you pass 70-178 exam at the first time!
Why choose Test4pass 70-178 braindumps
Quality and Value for the 70-178 Exam
100% Guarantee to Pass Your 70-178 Exam
Downloadable, Interactive 70-178 Testing engines
Verified Answers Researched by Industry Experts
Drag and Drop questions as experienced in the Actual Exams
Practice Test Questions accompanied by exhibits
Our Practice Test Questions are backed by our 100% MONEY BACK GUARANTEE.
Test4pass 70-178 Exam Features
Quality and Value for the 70-178 Exam
Test4pass Practice Exams for Microsoft 70-178 are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development.
100% Guarantee to Pass Your 70-178 Exam
If you prepare for the exam using our Test4pass testing engine, we guarantee your success in the first attempt. If you do not pass the Microsoft Business Solutions 70-178 exam (ProCurve Secure WAN) on your first attempt we will give you a FULL REFUND of your purchasing fee AND send you another same value product for free.
Microsoft 70-178 Downloadable, Printable Exams (in PDF format)
Our Exam 70-178 Preparation Material provides you everything you will need to take your 70-178 Exam. The 70-178 Exam details are researched and produced by Professional Certification Experts who are constantly using industry experience to produce precise, and logical. You may get questions from different web sites or books, but logic is the key. Our Product will help you not only pass in the first try, but also save your valuable time.
70-178 Downloadable, Interactive Testing engines
We are all well aware that a major problem in the IT industry is that there is a lack of quality study materials. Our Exam Preparation Material provides you everything you will need to take a certification examination. Like actual certification exams, our Practice Tests are in multiple-choice (MCQs) Our Microsoft 70-178 Exam will provide you with free 70-178 dumps questions with verified answers that reflect the actual exam. These questions and answers provide you with the experience of taking the actual test. High quality and Value for the 70-178 Exam:100% Guarantee to Pass Your Microsoft Business Solutions exam and get your Microsoft Business Solutions Certification.
Hot KeyWords On 70-178 test
We collect some hot keywords about this exam:
Test4pass , Pass 4 Sure , Test in Side ,Pass Guide ,Test King 70-178 exam | 70-178 pdf exam | 70-178 braindumps | 70-178 study guides | 70-178 trainning materials | 70-178 simulations | 70-178 testing engine | 70-178 vce | 70-178 torrent | 70-178 dumps | free download 70-178 | 70-178 practice exam | 70-178 preparation files | 70-178 questions | 70-178 answers.
How to pass your 70-178 exam
You can search on Search Engine and Find Best IT Certification site: Test4pass.com - Find the Method to succeed 70-178 test,The safer.easier way to get Microsoft Business Solutions Certification .
Microsoft 70-178 Exam Offical Information
1. A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering. What should you do?
A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task.
Answer: A
2. You have a Project 2010 schedule that contains the following tasks: Inactive tasksManually scheduled tasksManually scheduled summary tasksTasks that contain strikethrough font You want to save the schedule as a Project 2007 project. You need to ensure that no new milestones are created. What should you do?
A. Change all inactive tasks to active tasks.
B. Change all tasks that contain strikethrough font to tasks that include normal font.
C. Change all manually scheduled summary tasks to automatic scheduling.
D. Change all manually scheduled tasks to automatic scheduling.
Answer: C
3. You manage several projects. Each project has shared resources and work distribution. You need to ensure that you can adjust the workload for specific resources used across multiple project schedules. What should you do?
A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usage view to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Answer: C
4. You manage a project that specifies all constraint types to As Soon As Possible. You discover that one of your key tasks is scheduled to end prior to the targeted finish date. You need to display the targeted finish date on the default Gantt chart. What should you modify in the Task Information window?
A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box.
Answer: B
5. The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Answer: B
6. The project you manage has only part�\time resources. The part�\time resources work four hours a day from Wednesday through Saturday. You need to create a new calendar and set the calendar as the default for your project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Select the part�\time calendar from the Change Working Time window.
B. Set the calendar type to part�\time for all tasks.
C. Select the part�\time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box.
Answer: B, E
7. You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop�\down list box, select Project Finish Date.
Answer: D